22.10.2024 UBV / RIZ / OM Monthly meeting (telecon)

ANDES project

22.10.2024 UBV / RIZ / OM Monthly meeting (telecon)

  • 10:00-12:00 (CEST, Geneva, Berlin)

  • 9:00-11:00 (WEST, Tenerife)

Zoom link:

Join our Cloud HD Video Meeting

Meeting ID: 646 5813 5624
Passcode: 663130

AIP cloud folder:

https://cloud.aip.de/index.php/f/639359165

Agenda:

  • Meeting Agenda update

  • Action Item Follow up

  • PDR preparation

    • RIZ: Yevgeniy Ivanisenko (absent)

    • UBV: Joar Brynnel/ Christine Füßlein

  • SE update: REQ and ICD

    • UBV : Jörg Weingrill

    • RIZ : Bruno Chazelas

  • Optical design UBV/RIZ

    • UBV : Michael Weber / Jörg Weingrill

    • RIZ : Audrey Lanotte

  • Optical mount design

    • Roberto Simoes / Rocio Calvo Ortega / Roberto Varas Gonzalez

    • Svend Bauer / Hakan Önel - Grating mount

  • Optical bench and OB-camera interface design : Afrodisio Vega Moreno

  • MAIV at Tenerife and ASA design status: Manuel Amate

  • Detector unit : Ludovic Genolet

  • Vacuum tank: Pablo Santos Diaz

  • Thermal enclosure:

    • Analysis: Pablo

    • Design: Michael Sigwarth

  • 3D Experience PDM status and next steps

  • Next UBV/RIZ/OM Monthly meeting (telecon)

    • ?26.11.2024? Preliminary date

 

Minutes:

Project management: all dates for PDR are on the slides

AI: Manuel need updated date for AIT to check everything is ok with assembly halls in Tenerife.

System engineering :

BC: no news on the vibration requirement, not happy. Draft ICD for the coude, comments sent to PO

JW: work on doors ongoing. need some input for tests and validations

AI: Bave a meeting between BC and JW to align.

AI: BC to share the Alignement AIT/AIV plan draft that have been prepared to check that hypothesis are OK

Optical Design:

AL: ROM costs are comming, they are expansive.

Discussion about the colimators: geometry modification are considered for the costing. as well as gluing mechanical support pads and lightweigthing. Lightweigthing is an important cost driver. Assessment of the what we need to do will depend on the whole analysis. Lightweigting is not a big issue for the mounts. It is for the table and the overal weight.

UBV: ROM costs are also comming requested.

 

Mount design: Package delivered.

Discussion: Status of the ASA as before the delivery of the degrees of freedom requirements. To be seen with management if this can be improved for PDR documentation.

A document with questions suggestions etc for the next phases has been prepared by Roberto. It has already been shared with interested parties.

AI: BC to organize a meeting with roberto to analyse the answers to the compliance matrix.

Table design: Package delivered for UBV

Vacuum tank/Thermal Enclosure/Earth Quake simulations etc:

  • Vacuum tank rom IN, good providers identified

  • Vacuum tank FEM analysis ok

  • Outgasing study updated => Message mechanics, be it the tank, tables and mount need to be well cleand as they are dominating the budget.

  • Start Earthquake simulation for the whole assembly

  • Simulations of the Thermal enclosure show it is necessary to fix it to the ground at nasmyth for the eigen frequency (already OK)

  • situtation with 3d experience finalizong contracts on the side of UNIGE. discussion about when money can be spent on AIP side, it seems it will happen next year.

 

Next UBV/RIZ/OM Monthly meeting (telecon)

  • 26.11.2024 10:00 Geneva Time

 